| A.1- Rehabilitation of Irrigation and Flood Control Infrastructure |
IN PROGRESS |
55 |
0 |
8 |
0 |
0% |
0 |
0% |
| A.1.a- Dam/Spillway Rehabilitation Schemes |
IN PROGRESS |
27 |
0 |
4 |
0 |
0% |
0 |
0% |
| A.1.b- Flood Protection Schemes |
IN PROGRESS |
14 |
0 |
2 |
0 |
0% |
0 |
0% |
| A.1.c- Flood & Perennial Irrigation Schemes |
IN PROGRESS |
14 |
0 |
2 |
0 |
0% |
0 |
0% |
| A.2- Reconstruction & Rehabilitation of Roads and Bridges (KM) |
IN PROGRESS |
20 |
0 |
0 |
0 |
0% |
0 |
0% |
| B.1- Installation of RADAR System |
IN PROGRESS |
3 |
0 |
1 |
0 |
0% |
0 |
0% |
| B.2- Installation of AWS |
IN PROGRESS |
110 |
0 |
20 |
0 |
0% |
0 |
0% |